Reading the report, it looks like DND potentially saved two billion dollars.
In June 2006, DND estimated total costs at $6.9B when it sought and received Cabinet approval in principle (para 6.67). In July 2009, DND total costs were identified as $4.9B based on $2.3B actual committed capital acquisition and $2.6B budgeted in-service support for 20 years (para 6.48).
$6.9B (initial estimate) - 4.9 (actual) = $2.0B savings over the project identification, definition and development phases.
Food for thought.
Regards
G2G