RCAF to get only five test choppers as manufacturer faces $80 million fine
By: Murray Brewster, The Canadian Press 01/26/2012
Article Link
OTTAWA - The manufacturer of the air force's new maritime helicopter has told National Defence it will deliver only five test aircraft this year — opening the door to tens of millions of dollars in fines on a project the auditor general has said is late and over budget.
Sikorsky Aircraft Corp. is supposed to deliver a "fully mission capable" version of the CH-148 Cyclone helicopter by June, or face a further $80 million in contract penalties on top of $8 million the federal government has already levied.
Senior defence officials say safety certification of the aircraft is still ongoing and it's highly unlikely the giant U.S. aircraft-maker will meet its target, even though the program is years behind schedule.
"Sikorsky are only committing to deliver five by this year, which will be training aircraft," said a high-level defence source, who spoke to The Canadian Press on the condition of anonymity.
The Cyclones are the highly touted replacement for the CH-124 Sea Kings, which will mark a milestone 50 years in service in 2013.
Originally, the company was supposed to deliver its first chopper in 2008 and have the whole fleet of 28 on the flight line by end of last year. When it became evident a few years ago that schedule wasn't going to be met, the Harper government worked out a deal with the Stratford, Conn.-based corporation to provide a handful of scaled-down aircraft, which would be retrofitted later.
The so-called interim helicopters, which are minus combat systems, were supposed to allow crews to train. But only one helicopter was delivered last year and it arrived late, prompting the government to impose an $8 million fine.
Sikorsky has still not completed full certification of the training aircraft, although it is expected to happen sometime this year. But that's a long way from delivering a "fully capable (maritime helicopter), with all its mission software," which is what the contract stipulates.
When originally proposed 12 years ago, the cost was expected to be $2.8 billion, but that has ballooned to an estimated $5.7 billion, according to a 2010 report by former auditor general Sheila Fraser.
She criticized the Cyclone purchase as well as the plan to buy 15 CH-147-F helicopters, saying Defence turned what was supposed to be off-the-shelf purchases into a customization nightmares.
New Democrats have slammed the Harper government for apparently not collecting the initial $8 million fine.
But senior defence officials said that penalty and the anticipated additional $80 million will be deducted from future payments the federal government will make for maintenance on the helicopter fleet.
"The $8 million comes out of reduced payments and in-service support over time, which is to our advantage," said the senior official.