Very interesting.
I found a reference that Sikorsky proposed FBY for their failed V-92 "Marine One" proposal so it looks like Sikorsky has been looking for a development program/project for awhile.
Speculation . . . along comes Canada, launch customer for the H-92 and voila, FBY that Sikorsky has wanted to develop has a program that is "interested", a government agency (NCR) with money and a possibility to introduce an aviation "first" to the market but with shared cost burden
I'm pretty sure now FBY was not part of the original contract - not 100% sure but it looks that way. So it looks like FBY is an ECR to the project and it MAY be the reason for the 30 month schedule extension that is being sold as a "delay".
I don't know why they would do this, if indeed this is the actual case, but there are too many zipped lips here to make me think all is above board.
Sorry for being so cynical . . . just my experience on big Federal projects says this kinda things happens a lot. ECR's are the bread & butter of suppliers and the Snr Management often awards $$Bonuses for getting the government to pay for big buck ECR's. Some journo will dig up the whole story eventually . . . . who authorized what, when & why.
I'm not saying it is a wrong decision to delay for FBY - if that's the reason. They just seem to want to try and hide the reason for the delay/schedule adjustment. Stupid really, its always the cover-up that screws the pooch.
I've got some pilot friends with lotsa experience and contacts in the offshore oil helo business . . . I've emailed them asking for opinions on the S-92's.
I found a reference that Sikorsky proposed FBY for their failed V-92 "Marine One" proposal so it looks like Sikorsky has been looking for a development program/project for awhile.
Speculation . . . along comes Canada, launch customer for the H-92 and voila, FBY that Sikorsky has wanted to develop has a program that is "interested", a government agency (NCR) with money and a possibility to introduce an aviation "first" to the market but with shared cost burden
I'm pretty sure now FBY was not part of the original contract - not 100% sure but it looks that way. So it looks like FBY is an ECR to the project and it MAY be the reason for the 30 month schedule extension that is being sold as a "delay".
I don't know why they would do this, if indeed this is the actual case, but there are too many zipped lips here to make me think all is above board.
Sorry for being so cynical . . . just my experience on big Federal projects says this kinda things happens a lot. ECR's are the bread & butter of suppliers and the Snr Management often awards $$Bonuses for getting the government to pay for big buck ECR's. Some journo will dig up the whole story eventually . . . . who authorized what, when & why.
I'm not saying it is a wrong decision to delay for FBY - if that's the reason. They just seem to want to try and hide the reason for the delay/schedule adjustment. Stupid really, its always the cover-up that screws the pooch.
I've got some pilot friends with lotsa experience and contacts in the offshore oil helo business . . . I've emailed them asking for opinions on the S-92's.