I'll believe it when I see it.
They are intended as gap fillers and do not generally include long term sustainment.why does the UOR have to be limited? Seems very stupid to do everything twice if we get around to it. If we have an UOR for a capability either because we have let it atrophy or just dont have it then its urgent right versus replacing things on a somewhat regular rate. Is it because everything is urgent?
Then why is no one holding them accountable? Are you suggesting every single officer at DLR is useless? Where are the SNCOs doing their job to hold officers to account when dereliction of duty is happening? Why aren't heads rolling over the inefficiency?Officers who have no sense of the time value of money who propose solutions that are unaffordable that spend multiple years circling the drain can step forward.
Then why is no one holding them accountable? Are you suggesting every single officer at DLR is useless? Where are the SNCOs doing their job to hold officers to account when dereliction of duty is happening? Why aren't heads rolling over the inefficiency?
Big ole sigh on my part is all I can say to that.
Meanwhile, the 2023 Auditor General's Report...
The staff at DLR/ADM(Mat) are working within the parameters set by much bigger fish in the pond.Then why is no one holding them accountable? Are you suggesting every single officer at DLR is useless?
Seeing a SNCO (Sergeant), let alone the compliment of Warrant Officers of varying rates, in the Projects world sees them as Technical SMEs and less Comd Team partners.Where are the SNCOs doing their job to hold officers to account when dereliction of duty is happening?
What is your definition of inefficiency?Why aren't heads rolling over the inefficiency?
That should be taught in every class.What is your definition of inefficiency?
To a dude who is missing the capability they need right meow to keep them and their buddies alive if SHTF, its wholly inefficiency.
To various ADMs, DMs, Ministers, and our own CoC... they see a mechanism to ensure every defence dollar is thoroughly spent in the most prudent and fiscally responsible manner. If that takes 20 years, well, at least they did their due dilligence.
Where we fall down every time is that we refuse to see the hybrid approach of expediency met with value for money.
If we (CAF) know that our needs and wants are very low in the pecking order... we need to meet the other priorities half way whenever possible.
The staff at DLR/ADM(Mat) are working within the parameters set by much bigger fish in the pond.
ISEB, TBS, PSPC, and a host of people who haven't even heard the word "CADPAT" ensure DND's and even less so the CAF's priorities are subordinate to a host of other political ones.
LCol Bloggins can be the best and smartest Project Director in history, but he's still bounded by a bureaucracy that very much would rather not spend a dime if they didn't have to.
Seeing a SNCO (Sergeant), let alone the compliment of Warrant Officers of varying rates, in the Projects world sees them as Technical SMEs and less Comd Team partners.
You'd be more likely to see Jalapeño Poppers in the mess on Thursday than you would a Sergeant or WO taking and officer to task in a project cell.
What is your definition of inefficiency?
To a dude who is missing the capability they need right meow to keep them and their buddies alive if SHTF, its wholly inefficiency.
To various ADMs, DMs, Ministers, and our own CoC... they see a mechanism to ensure every defence dollar is thoroughly spent in the most prudent and fiscally responsible manner. If that takes 20 years, well, at least they did their due dilligence.
Where we fall down every time is that we refuse to see the hybrid approach of expediency met with value for money.
If we (CAF) know that our needs and wants are very low in the pecking order... we need to meet the other priorities half way whenever possible.
The others (ADM, PSPC, ISED, et al) in turn need to understand we are not buying furniture for Service Canada offices over the next 20 years; we need these systems to keep people alive in some cases and to project that foreign influence the government asks of us. That may mean skirting the procurement process, sacrificing benefits to Canadian industry, or gasp buying MOTS/COTS from international vendors.
There are a lot more fingers in the procurement pie than just the staff in DLR.Are you suggesting every single officer at DLR is useless?
That is not the job of Sr NCOs. Also, unlike in a regiment, the WOs & MWOs in DLR, CFD, CProg, ADM(Mat), etc are generally not more experienced than the officers in the business of the unit.Where are the SNCOs doing their job to hold officers to account when …
Army PDs are Majors, Captains, and sometimes MWOs. Many PMs in ADM(Mat) are LCol (though they should probably all be Mr/Mrs/Ms). So your PM (whose priority is schedule & budget) is typically senior to your PD (whose priority is ensuring the right capability).LCol Bloggins can be the best and smartest Project Director in history, but
Maybe if the Army was a stronger sponsor of its requirements it would see improved responsiveness from Mat Group?Army PDs are Majors, Captains, and sometimes MWOs. Many PMs in ADM(Mat) are LCol (though they should probably all be Mr/Mrs/Ms). So your PM (whose priority is schedule & budget) is typically senior to your PD (whose priority is ensuring the right capability).
Maybe. What would that look like?Maybe if the Army was a stronger sponsor of its requirements it would see improved responsiveness from Mat Group?
More LCol and Maj PDs…at the working level. Army SRBs also seem to have lesser co-chair attendance than the other services from what I observed.Maybe. What would that look like?
It might look like it did 50 or even 35 years ago when there were, generally, three "partners" in any project:Maybe. What would that look like?
…the ‘lads’ still respect him greatly. Had he not been freed when he was, I’d wager some bubbas would have taken leave to take a short vacation to Africa.In later years, when the DM, the much feared (but also much respected) Bob Fowler, got involved DND almost always won even when John Manley was Minister of Industry and Kevin Lynch was DM of that department.
UORs are also known as Unforecasted Operational Requirements which indicates they are not part of the forecasted planning process for combat capability acquisition. A proper project will examine for and incorporate not just the equipment acquisition but also the adjustment if any to the manning structure of the agency deploying it, any additional infrastructure needed to support it , its life cycle management and any capability divestments that are generated as a result of its deployment.why does the UOR have to be limited? Seems very stupid to do everything twice if we get around to it. If we have an UOR for a capability either because we have let it atrophy or just dont have it then its urgent right versus replacing things on a somewhat regular rate. Is it because everything is urgent?
I know a number of gunners who've worked in the DLR world and none of them are slouches. The trouble is that its a soul sucking job. Procurement is such long cycle that one never sees the delivery of the systems one is working on coming to fruition during one's tour. Projects frequently make it to the cusp of approval only to be supplanted by something else because $ became unavailable or priorities shifted during the interval.Then why is no one holding them accountable? Are you suggesting every single officer at DLR is useless? Where are the SNCOs doing their job to hold officers to account when dereliction of duty is happening? Why aren't heads rolling over the inefficiency?
CCV and LRPRS (Long Range Precision Rocket System - not MLRS but something more HIMARSy) both came into vogue as part of the Family of Land Combat Systems in 2006. LRPRS was one of the top six projects the army was advancing in 2008 (as was CCV, TAPV, CIED, LWTH, and LAV3 UP)(LWTH ie the 25 additional M777s was funded and approved and delivered - as was TAPV, LAV UP and CIED). CCV died a horrible death on December 19, 2013. It had been funded (to the tune of $2.1 billion) LRPRS never got that far along the path. I don't think it was ever funded. (I'm not sure, my research for WAFG Vol 2 will be looking at that later this fall) I've heard that in 2010 it was still on stream but and was almost a done deal but quickly turned into a twinkle in people's eyes and went into limbo. CCV didn't replace LRPRS. I think it was always below CCV in the order of priority even before a fixed end date to Afghanistan was promulgated.So an Artillery commander of the Army may well be prioritizing MLRS in 2007, but he moved on (less than 40km), but other, higher priorities like CCV replaced that. And so on...
I know a number of gunners who've worked in the DLR world and none of them are slouches. The trouble is that its a soul sucking job. Procurement is such long cycle that one never sees the delivery of the systems one is working on coming to fruition during one's tour. Projects frequently make it to the cusp of approval only to be supplanted by something else because $ became unavailable or priorities shifted during the interval.
Yeah, I didn't want to leave JAG CIMP before it rolled out but at age 60 you become corporately unemployable (presumably senility sets in on your 60th birthday - it might have but I didn't notice any change from the day before )A former boss of mine once told me that Force Development is a great field to work in, so long as you can consistently follow the cardinal rule of "don't get emotionally invested into any of your projects" for the reasons you described above. I generally don't have the strength of character to completely divest myself from my professional projects, and for that reason I've never worked in FD.
Estimates from five years earlier are refined as the project enters OA. Oh no, inflation! That estimate will now only buy 75% of the quantity we think we need. Let's circle back and validate the requirement again (another year or two of inflation). Numbers change a bit, but now, since the budget hasn't changed, we can only buy 60%.
Let's look at other projects, lower in priority. But they have champions (for good or for ill) protecting them. We just lost another year, and can now only fford 55% of the capability we are replacing - that now is three years closer to obsolescence. And technology has advanced - do we double down and buy something that will be obsolete on arrival?
The Army also suffers from internal warfare - the RCN wants ships and the RCAF wants planes. So an Artillery commander of the Army may well be prioritizing MLRS in 2007, but he moved on (less than 40km), but other, higher priorities like CCV replaced that. And so on...